Energy Update

  • NEA : 9697 MWh
  • Subsidiary Company : 2149 MWh
  • Private Sector : 27548 MWh
  • Import : 0 MWh
  • Tripping : 80 MWh
  • Energy Demand : 39474 MWh
  • NEA : 0 MW
  • Subsidiary Company : 0 MW
  • Private Sector : 0 MW
  • Import : 0 MW
  • Tripping : 0 MW
  • Peak Demand : 1830 MW
2024 December 22,Sunday
×

Kathmandu: Betan Karnali Depositors Hydropower Limited (BKDHL), a subsidiary of the Employees Provident Fund (EPF), will be starting the construction work of 439 MW Betan Karnali Semi-reservoir Project from next year.

To expedite the process, the company has recently called for ‘Letter of Intent’ to select an international consultant for the project’s supervision. According to BKDHL, the civil work of the project will start from 2023 end.

Deepak Rauniyar, manager of the project, said they will call for a global tender to appoint a consultant. According to him, they will then go into a bidding process to construct the related infrastructure of the project that is targeted to be completed by 2028.

The detailed project report prepared by NEA Engineering Company shows that the cost incurred for the construction will be Rs 74 billion, while it will increase up to Rs 88 billion in addition to the banks’ interest rate. Rauniyar said there may be some variation in costs due to inflation and rise in price of the US dollar.

The project is estimated to produce a total of 2.40 million units of electricity annually. It is projected to fetch an earning of Rs 14.50 billion in the first year while the annual revenue will go up to Rs 18.37 billion after nine years of production.

Global IME Bank will be leading the banks’ consortium to fund the project. Sunrise Bank and Nepal Infrastructure Bank will be other financing partners for the project. These banks will be investing a total of Rs 54 billion.

The issued capital of BKDHL is Rs 20 billion and its paid-up capital is Rs 10 billion. The EPF has assigned 40 percent shares of the project to its 600,000 depositors. According to the EPF, it will be investing Rs 8.40 billion of its depositors in the project construction.

The EPF will hold 15 percent of the project’s equity shares, while Nepal Electricity Authority will have 10 percent, Electricity Production Company Limited will have 10 percent and an additional 13 percent will be generated by issuing primary shares to general people.

Likewise, two percent of the equity will be allocated for deprived community people and 10 percent will be provided to project affected local people. The electricity produced by BKDHL will be evacuated through a 400 kV transmission line to be constructed by National Transmission Grid Company Limited.

Conversation

© 2024 Urja Khabar. All rights reserved
Contact for advertisement +977-1-5321303