Energy Update

  • NEA : 9697 MWh
  • Subsidiary Company : 2149 MWh
  • Private Sector : 27548 MWh
  • Import : 0 MWh
  • Tripping : 80 MWh
  • Energy Demand : 39474 MWh
  • NEA : 0 MW
  • Subsidiary Company : 0 MW
  • Private Sector : 0 MW
  • Import : 0 MW
  • Tripping : 0 MW
  • Peak Demand : 1830 MW
2024 December 4,Wednesday
×

Kathmandu: Happy Energy Pvt Ltd has started preparation work to build 40 MW Upper Sankhuwa Khola Hydropower Project (USKHP).

The USKHP will be a run-of-river type hydropower project and will be located in ward numbers 1 and 2 of Silichong Rural Municipality of Sankhuwasabha district. According to the company, it has finalized the detailed project report of the project while the environmental impacts assessment has been submitted to the Ministry of Forest and Environment for the final approval.

The project to be constructed in Sankhuwa Khola will have a 500 meter net head. It will have the headrace tunnel of size 3,650 meter and a 180 meter audit tunnel. Similarly, the design discharge rate would be 9.61 cubic meters per second.

The USKHP is projected to produce 235.40 GWh of electricity annually, which will include production of 164.77 GWh in peak season and 70.63 GWh in dry season). A tailrace of 40 meter in length will be built to return the used water back to the Sankhuwa River. A 220 kV transmission line will be built to supply the electricity produced by the project to the national grid.

Of the required 19.85 hectares of land, 12.63 hectares of the public forest, including that of Makalu-Barun National Park and remaining 7.22 hectares of private land will be utilized for the project construction.  

The USKHP construction is estimated to cost Rs 7.88 billion. It will include 70 percent loans and 30 percent equity shares. 

Conversation

© 2024 Urja Khabar. All rights reserved
Contact for advertisement +977-1-5321303